The BR-101 will undergo work in the south of Santa Catarina in March. According to the schedule, work on the track will begin this Monday (13th) and will last until the 19th of the current month. The information was made public by CCR concessionaire ViaCosteira, responsible for the stretching. Anyone who intends to drive on the road should pay attention to some places where traffic can be half-lane.
Among the planned works is the restoration of the road surface, as well as the repair and conservation of the highway. Some of these services require lane closures, which can slow down or delay vehicles.
CCR ViaCosteira also indicates that the opening hours are dynamic and subject to change. For example, in the event of adverse weather conditions, flight schedules will be rescheduled.
View the road resurfacing and repair schedule
According to CCR ViaCosteira, the following locations will have a lane ban between 07:00 and 17:00:
- Paulo López: Between 249 and 251 kilometers, southbound lane ban;
- Lagoon: between 299 and 304 kilometers – the strip is closed to the north;
- Tubarao: between 345 and 346 kilometers – a strip in a northerly direction; This
- Sangão: between 258 and 259 kilometers – there will be a blockage on the northern lane.
The concessionaire urges users to be especially careful and observe signs and speed limits when passing through the indicated places. At these points, workers will be working very close to the runway.
There will be a blockade between the cities of Capivari de Baixo and Tubarao from 07:00 to 18:00 on the secondary road BR-101. The road surface repair will take place between 327 and 441 kilometers in both directions of the road.
Some work will be carried out without the need to close the lane. Services will be provided from 07:00 to 18:00 as follows:
- From Paulo López to Passo de Torres: preventive maintenance and lighting between 245 and 465 kilometers;
- Paulo Lopez: in the area of the Morro Agudo tunnel, at the 257th kilometer; This
- Tubarão: in the Morro do Formigão tunnel, at kilometer 338.
Runway conservation and maintenance work
Vertical signage services, walkway cleaning, repair and painting of special artworks will be carried out along highway kilometers 245-456, between the municipalities of Paulo López in Greater Florianopolis and Passo de Torres on the south coast. These actions do not involve blocking lanes.
According to the concessionaire, the work schedule also includes cleaning concrete fences, repairing drainage, pruning trees and shrubs, installing horizontal signs, cleaning signs, installing dividers, installing metal protection, and removing debris.