![Since the delivery date of the Road Contour is unknown, Arteris has already been fined more than R$500 million. Since the delivery date of the Road Contour is unknown, Arteris has already been fined more than R$500 million.](https://beemagzine.com/wp-content/uploads/https://static.ndmais.com.br/2023/09/br-101-tera-interdicoes-no-mes-de-setembro-por-obras-do-contorno-viario-veja-onde-800x450.jpeg)
According to the article, ANTT (National Land Transport Agency) has already fined Arteris 820 times. The concessionaire responsible for the section from Palosa (SC) to Curitiba (PR) was fined R$512 million.
![Greater Florianópolis road outline Greater Florianópolis road outline](https://static.ndmais.com.br/2023/09/br-101-tera-interdicoes-no-mes-de-setembro-por-obras-do-contorno-viario-veja-onde-800x450.jpeg)
The data covers the entire period of the concession and includes contractual and regulatory violations related to road surfaces, horizontal and vertical signage, safety and security features, special works of art, highway operation and non-performance of works.
It is important to remember that these figures cover the entire area provided, not just delays along the road contour.
Last week, Bom Dia reported that the long-awaited project, considered the largest in terms of infrastructure in Brazil, will not be completed this year.
Visit
The visit of ANTT General Manager Rafael Vitale to the work on the construction of the Greater Florianópolis road contour is confirmed for the morning of this Friday (20).
Senator Espiridian Amin (PP) will follow the agenda, which is surrounded by expectations, to determine a new completion date.
Arteris did not “allow” the press to accompany the visit.
Source: Ndmais